Construction week 24 & 25: lots of snow shoveling

We had record snow fall in Ottawa last week. Apart from shoveling, here's a quick summary from the last couple weeks:

  • roof sheathing, membrane, and metal roof 
  • truss blocking
  • window bucks installed, reinforced and double-checked for size
  • insulation started

Earlier today, Mark gave our first public tour of the house. We had around 15 people brave the construction site and cool temps to listen to how our house is coming together. Thanks to all who came out. Hope you learned something.

Here's Mark introducing our home on the tour.

Here's Mark introducing our home on the tour.

This upcoming week, Mark will finish insulating. And our windows are getting installed. EeK!!!

Comment
Share

Construction week 23: roof trusses

ottawa-greenconstruction-roof-trusses

Mark did a pretty great job explaining the roof truss install, which happened this past Tuesday. Thanks to Mark Greenacre for helping out the team. With the remaining days, they built additional frame walls to support the trusses and added the cross bracing to keep it square.

This upcoming week, they'll be finishing the roof prep and installing the roof sheathing. The roofers are due to arrive Wednesday! We are going with a black/grey metal roof, which will be seen by no one.

I had a couple concerns with the metal roof at first:

  1. Would it attract lightening bolts?
  2. And would the dark colour add to the cities 'heat island effect'?

I'm glad to report, through diligent googly research, that I need not be worried, in either case.

If you're flying your drone overhead, our roof will look something like this:

metal roof

 