Construction week 51: the final countdown

The one week (less than!) countdown begins. Our official move day is Friday, September 2nd. My daughter's 4th bday. Sure to be a memorable one.

Our ceilings aren’t the only destination for wood in our house. Wood on the outside, wood on the inside. I’m starting to think of our house as the ‘wood box’: where a simple, honest shape meets a simple, honest material. Anyways, this week was focused on floors and stairs. Both receiving the full white ash treatment. 

Stairs
Our super-awesome-carpenter-guy Graham was tackling stairs. The stairs are three inch thick slabs of white ash (from the Wood Source). They have been designed to be supported by the stair metal brackets Mark had made and installed. The wood requires a small channel carved into its ends, so it can slide onto the bracket, sandwiching it, and hiding it so that the wood ‘floats’.

And this is where I segue over to Graham praise. He goes above and beyond. We are incredibly lucky to have him on our project. He possesses the same passion and care for quality and craftsmanship as does Mark. For instance, in order to carve our stair channels, he needed a better tool for the job, a Festool. He couldn’t find one in Ottawa, so he drove to Kingston to purchase it (hour and a half drive), drove back, and took a lesson on how to properly use it that same night. He was on site the next day figuring our how to precisely carve these channels at varying subtle angles, in order to get them just right. And he did. He also makes a great DJ. No Chez 106 on our site.

The only stair hiccup was a small mistake made by Mark with measurements. One floor riser was ⅜” taller than others, which apparently isn’t ‘to code’. I’d bet none would be the wiser if we kept the ⅜” difference, but to the uncompromising Mark Rosen, this surely wouldn’t do. So we had all the stairs planed down ¼” so that each step is now at 100% equal height. Unfortunately, we had to bring them back to the Wood Source to get them done. So all the work on the stairs won’t pay off until early next week and the temporary stairs had to get reinstalled. Wah-wah.

Stairs go in

Stairs go in

Stairs come out

Stairs come out

Floors
Drumroll…

 

 

 

 

 


No squeaks! Rejoice rejoice! 

A full glue down was the trick for our 5” white ash, site finished hardwood. We used two different polyurethane flooring glue because the local supplier, Dragona, didn’t have enough in stock to do all in one brand. We used both Maipei ultrabond eco 995, and Roberts 1540. We also stapled, but only when necessary to keep the boards toight. 

Mark, Graham and Sebastian have been working on the floors, burning the midnight oil. Working until midnight the last three nights in a row. We rented some machines to sand the floors down ourselves too. We were going to hire out the finishing job, but we’d have to wait until Wednesday to do so. And with our September 1st move-in coming up, we just couldn’t. 

Everyone unanimously vows, repeatedly, that this would be their first and last glue-down hardwood floor + finishing install. The glue was the worst. Thankfully, they are also in unison upon the fact that they look bloody fantastic. 

ottawa-canada-passive-house-architect
ottawa-canada-passive-house-architect

Oiling the floors happens this week.

Appliances
With the exception of our laundry machines (because the wood floor has to come first), all our appliances have been installed! So what appliances did we choose for our Passive House build? I’ll write a separate post on this. For now, just know they are in. Mark was boiling water every 10 minutes, and timing it, on our new induction cooktop. He even took video to show me, on the first night in was installed, and now I’m posting it here for everyone to see. It's just about the least exciting 4 minutes of your life, but not for Mark. lol.

Our downdraft ductwork. Yowzers!

Our downdraft ductwork. Yowzers!

Temporary railings
We had to install some temporary railings to get occupancy. Must admit, we cried a little on the inside putting the hideous, weathered plywood up on our mostly finished house. But at least it’s safe and will get us to permit. It should only be a few weeks of us living with them in this state until the permanent railings are ordered and installed.

It hurts!

It hurts!

Yard cleanup
I wish I had thought of Kijiji earlier on in the build. I used it to get rid of all our extra building material. And it was so easy! People will take anything. Especially if you say it’s free. It would have saved us a whole dumpster of waste, at least. Lesson learned. Now that most of the extra building material is off the lawn, it’s starting to feel like a proper house (our landscaping is on hold, so it’s a massive weed garden, but it’s better than a building supply lot).

Plumbing
Toilets, faucets, showers, bathtubs, drains, heat exchanger connections, floor drains, condensation traps, backflow valves. We’re ready to pass our plumbing final inspection, which will take place on Monday. Our diswasher and espresso machine still need to be hooked up, but aren’t required for occupancy. I’d like to take a moment to admire Nathan’s skills. Our mechanical room is a work of art. Look at all the cool copper handiwork. It really adds to the engine room feeling of the house. Of all the beautiful spaces in our house, it might just be Mark’s fave :)

Check out our sweet stack

Check out our sweet stack

Occupancy
And finally, our occupancy. We called for the city to come on Tuesday. Usually they are required to come within 24 hours of a request. But for some reason, they were overbooked, and we couldn’t get anyone out this week. So someone should be coming on Monday. We were really hoping for someone to come on Friday, to give us an idea on what our weekend ‘occupancy to-do’ list would but unfortunately, no dice. 

Move
Meanwhile, while Mark’s working on site into the late hours, I’m at home packing boxes. I pulled the trigger and managed to find a moving company less than a week in advance of the move date. The thought of moving all the boxes and furniture ourselves, with all the work remaining at the house and all the work to date, was enough to shatter me into a million pieces. Phew! When my mom was visiting last week, she was with her Australian boyfriend, who trained with their military once-upon-a-time. He expressed concern that we were starting to show signs of severe exhaustion akin to his military training where they push you until you break, and then keep pushing. Maybe. But at least we have our new spa to unwind in at the end of the long day :)

Ahhhhhhh

Ahhhhhhh

Construction week 49: 2 weeks until occupancy

In order for us to move in, we need to obtain an occupancy permit from the city. This does not mean our house will be complete, but means it has all the necessary mod cons for us to occupy it safely. We’re prioritizing tasks that will get us to occupancy. We will have toilets, for instance, but no Interior doors. 

Here's the roundup from week 49.

Deck
The deck platform and stairs are finished, with the exception of the final stairs to ground level. We need our final grading to be completed first, which should bring our number of stairs down to 2 instead of 4. We also need some railings. These will most likely be temporary railings, to get us to occupancy.

Looking down from the roof deck

Looking down from the roof deck

Railings still to come

Railings still to come

ottawa-canada-architect-passive-house

Tile
Benjamin was at the house and finished laying the tile in our bathroom. It was a lot of tile, extending all the way to the ceiling (which will get the special wood-treatment soon). It’s quite dramatic.

In progress

In progress

Countertops
Our island counter was installed. And quickly covered as to not incur damage. We chose Caesarstone because it's zero-maintenance.

Caesarstone in Concrete colour option

Caesarstone in Concrete colour option

Electrical
We have lights! Now there’s no excuse for us not to work late. Most of our fixtures are in. Minus a few feature lights. Thank you Yves, and sorry for choosing pot lights that tore up your hands during the install :(

The best tip we received for lighting was to consider what you want to light. With stairs, for example, it's important that the stairs are lit, so you can see where to put your foot, and not the entire stair well. And with general room lighting, it's the walls that need defining, so direct your lights towards the walls and not the middle of the room.

Stairs are beautifully lit

Stairs are beautifully lit

Look Ma, no pendants!

Look Ma, no pendants!

Plumbing
We have a toilet in the house! This is majorly exciting for me. I don’t have to use the porta-pottie when I’m working on site anymore! And we can finally get that thing removed. The remaining fixtures will be installed this week.

This little throne I call my own, I aim to keep it neat. So darn your soul, pee down the hole, and not upon the seat. ~ classic outhouse quotes

This little throne I call my own, I aim to keep it neat. So darn your soul, pee down the hole, and not upon the seat. ~ classic outhouse quotes

Vanities
Mark assembled and mounted our bathroom vanities. We opted for Ikea vanities. We went through multiple explorations, trying to find an alternative, but just couldn’t stomach the associated costs. We almost pulled the trigger on a custom bent metal vanity that we designed, but in the end, it left us with too many unknowns (and no drawers). In our bathroom, we have an Ikea base that we’re pairing with a Caesarstone counter and Toto vessel sink. It will be partially custom, in this case. It will look great, but I really wish that Ikea made a 1 drawer depth vanity. I prefer the proportions, but am sure the extra drawer will be put to good use.

Ceiling
Mark and I had this crazy idea that our sloped ceiling would look fantastic if it were clad in wood. It seemed like a good idea at the time. And I’m sure it will become a good idea again, after all is said-and-done. But now? It’s a lot of effort. 

The order of things is a follows:

Step 1: lay plywood
Step 2: level and strap ceiling
Step 3: paint everything black
Step 4: install lighting tracks
Step 5: oil and stain ash planks
Step 6: mount ash on strapping
Step 7: admire hardwork 

Graham and Sebastian helped to progress the ceiling over the weekend. Finishing off the strapping in our bedroom and bathroom. They moved on to the main space, over the void, and set up what they nicknamed ‘the death trap’ – a precarious platform to help them reach across the 2-story open space (aka. void) that exists in the middle of the house. It isn’t actually as precarious as the name makes it sound. The hope is that they finish the strapping tomorrow, leaving the death trap setup for Mark or I to paint everything black. Yay. 

It really will look fantastic…

Inspiration photo — our ceiling should look something like it

Inspiration photo — our ceiling should look something like it

I see a ceiling and I want it painted black

I see a ceiling and I want it painted black

The so-called 'death trap' or 'widow-maker' spanning the void 20' up

The so-called 'death trap' or 'widow-maker' spanning the void 20' up

Landscaping
We’re working on a landscape plan with Rebecca James, an architectural technologist with a horticulture degree. Landscape design doesn’t pay the bills, so she does it on the side of her regular 9-5. Because she loves it. My kind of girl. We’re happy with what’s she’s shown us so far. 100% we won’t have landscaping for occupancy, nor this year for that matter, but we want to set up the design now, so we know what we’re working towards in the future. I wish it could all happen RIGHT NOW!!!!

Project management
On the project management side of things, we’re hoping to finish electrical and plumbing this upcoming week so we can go for our next construction mortgage withdraw. In the meantime, we’re racking up lots of travel points on our credit cards. One of these days we’ll want to leave Ottawa and our new house, so those points will come in handy. One of these days...

Our heads are down and we're ticking tasks off our lists faster than new ones are getting added. It's looking promising *knock on wood* for us to make the occupancy call on Aug. 23rd. My mom is visiting from Vancouver this week and has taken our kids to a cottage. I got to spend the whole weekend working on site, And will have my evenings to contribute this upcoming week too. Miss the kids like crazy, but won’t have much time to do so. Lots of site tidy-up and painting on my plate. And getting ready to move. Hopefully for the last time.

Construction weeks 33 & 34 – plumbing, hvac and more

manifold system

manifold system

plastic in the walls

plastic in the walls

Wow, it’s been a couple weeks since I’ve provided an update. The house has been relatively quiet with only one or two people working at a time. That has since dramatically changed…

Nathan, from Ackland Plumbing, has finished the first rough-in phase for plumbing. We’ve got spiffy (BPA-free) breathable supply pipes running through the house, and a purple one which supplies the grey water. He was explaining to me how, just 10 years ago, a different kind of plastic pipe was getting installed in Canadian houses, one which does not breathe and where water stagnates and becomes unsafe for drinking. Insurance companies will not insure these houses and lawsuits are being filed against the building code. Lesson learned: what seems like a good idea today, may very well prove to untrue tomorrow. And wet things need to breathe, trapped moisture is the enemy of building. I digress. Back to our house.

Nathan managed to carefully maneuver all supplies and drains in and between our open floor trusses and walls. The design of our house helped to facilitate this, with Mark stacking all the plumbing and electrical to one side of the house, over the mechanical room. (This poses absolutely no risk Myles btw (comment from previous post), it’s actually a really clever thing to do when building because all utility runs are minimized in terms of materials and labour). We’ve received numerous compliments on Nathan’s handiwork and it passed the plumbing inspection no problem-o. He’s as excited as we are to have a neat and tidy mission control in our mechanical room, where we’ll go copper for added ‘wow’ factor. Good stuff.

wood fibreboard clads the house until the siding gets installed overtop

wood fibreboard clads the house until the siding gets installed overtop

the cardboard box phase

the cardboard box phase

Speaking of passing inspections, we also passed our building envelope inspection. Hooray! We were nervous about this one because we weren’t sure how the inspector would feel about forgoing the traditional Tyvek weatherproof house wrap for our wood fibreboard. The wood fibreboard is more common in Europe and is not often seen on our side of the pond. Mark provided specs to the building inspector and explained it to him. We’re fortunate to have an experienced and open-minded official. But there’s no doubt to anyone walking through or around our house that it’s a well-built, thoroughly considered house.

zehnder hrv unboxing
zehnder hrv

And back to the mechanical room. Hans from Pinwheel Builds met with Mark and dropped off our new Zehnder HRV and heat exchanger along with coils of flexible plastic pipes, which are to be our house’s air ducts for circulating what little heat we require. It’s a pretty groovy system. We won’t have any gross floor ducts, bulkheads or metal work in our house. All you’ll see are small 8” diameter circles mounted to the occasional wall and ceiling to circulate air. Mark went over his plan with Hans and has started installing the ducting himself. Unboxing the parts was better than Christmas for Mark. He was so excited.

parapet roof

parapet roof

new carhartts

new carhartts

From here on out, Mark will be spending as much time as possible working on the house himself. He bought himself a spiffy new pair of Carhartt overalls for the task ;) In addition to starting the ducting, he finished the parapet (a fancy word for structural railing) on our flat roof, cleaned up the front and back yards, and hosted another tour. This last one saw around 30 people who joined as guest of Malcolm Isaacs, who runs the local Passive House courses and is a director of the Canadian Passive House Institute.

brown ash cabinets

brown ash cabinets

ash and gloss white

On the backend, we ordered our kitchen. Another hooray! Finally. There were a few back-and-forths during the homestretch, which prolonged the process, but were key for getting the details ironed out. We’re really excited about it. We ended up going with Astro Design Centre and have had a great experience working with Dean Large. He ‘gets’ us, in terms of design, and was able to add real value to our design experience, which we really appreciated. Astro also had the finishes we liked the most, at the best price. For example, a gloss white was the same cost as a matte white (typically gloss costs more). And we don’t want any hardware, we want recessed handles (a no hardware look typically costs more). We went with the Astro house brand in white gloss for all the cabinets except those on the backside of the island. The backside of the island faces the living area. For these cabinets we chose a sand-blasted (i.e. textured) brown ash. Haven’t ordered our countertops yet. That’s next.

Following suit, we made a decision on our wood flooring and placed the order. We’ve decided to go with white ash from the Wood Source. The same white ash that the city of Ottawa has felled throughout the city to thwart the Emerald Ash Borer. It will be sympathetic to the island wood. We also decided to order some extra wood for the sloped ceiling, which spans our open space, over the master bedroom and loft. A slatted wood ceiling will allow for clever lighting hacks. We’ll be able to hide much of the hardware behind the wood so that we only see what we want to see and can get away with using less expensive fixtures at no aesthetic compromise. It will also look incredibly beautiful. It’s a win-win.

As alluded to earlier, the house is buzzing again this week. Siding has begun amongst other exciting things. Do stay tuned and lookout for another Mark Periscope. He broadcast just today. And hope you’ll join the next house tour!

Comment