Trees and doors (and a whole lot more)

The jungle

The jungle

We have yet to break ground and shrubbery is quickly taking over. Our windows and doors are already on the shipping container, headed over from Euro-ville. When we ordered them, we thought we’d be waiting for them to arrive and not the other way around. Cut us a break would ya??!! It’s our first time building a house…

My grandmother would always tell us kids, as we impatiently asked about dinner, “good things come to those who wait”. Argh. It killed me then and it’s killing me now. I keep channelling Granny as things keep getting delayed. It will be worth it. 

I’m beginning to realize that there is a direct correlation between my blog writing and my emotional and mental state. When I’m excited, and progress is being made, there’s an influx of posts. When the opposite is true, things remain somewhat stagnant. It is my full intent to write as frequently as possible, reporting on all house happenings, and not just when I ‘feel’ like it. There’s just not a whole lot to report yet.

Last week, Mark prepped more drawings (electrical and plumbing) and distributed them to multiple trades for estimates. He accidentally wrote 145 Bayswater on the plans (instead of 105) and has caused some confusion. Our neighbours at 145 have just started building a house on an adjacent empty lot as well. Imagine the surprise of the excavator trade showing up at 145 to see there was already a hole in the ground. Our neighbour texted me to say someone was there scratching his head about the drawings the architect sent him. Du-oh! 

I have been consulting with several tree service teams so we can get the lot cleared and ready to build on. It’s always more complicated than at first thought. There are some trees at the front (closer to the sidewalk) that we have to get permission from the city to cut. And there are some growing over the electrical lines on the alley that we have to get Ottawa Hydro to cut. Then we bring the tree team in. 

Our wonderful orange house neighbours have gone ahead and started some of the clear cutting for us. The large apple tree is down! They want to burn some of the wood in their fireplace. I have requested that they leave some of the larger diameter portions as I would like to mill it and turn it in to something for the house. What that something is, remains to be seen. A powder room counter top? A stair landing in the dining room? TBD. It’s beautiful old-growth apple tree and was in the centre of our lot for 100+ years. It’s a part of the land and needs to be a part of the house.

El stump'o

El stump'o

Good news on the silver maple front: it’s healthy! There is a bit of a concern that we’ll do some damage to the root system when we excavate. The house is far enough back, though, that any damage will be kept to a minimum (we hope!). We’ll probably just do some deep root fertilization to help it get through the year, and look at cosmetic trimming in the future. The canopy is good as-is. No need to unnecessarily add stress to the tree at this stage.

What else? We are meeting someone from Ottawa Hydro at the lot tomorrow morning to discuss how we will connect to the main line. And we are making some big decisions on the backend that we hope to share soon enough. Oh, and did I mention we ordered blue doors? Reflex blue. The bluest of the blues. Couldn’t expect us to go entirely neutral with neighbours as colourful as ours, could you?

That's blue baby! 

That's blue baby! 

Pre-fab no more

We’ve thrown the towel in with our pre-fab builder. The red flags have been flying for a while now. We’ve finally decided that we would feel more comfortable building the good old fashioned way — with site framing. 

Despite this setback, we're feeling much more comfortable with where the build is headed. With tried and tested techniques and builders. We’ve got several enthusiastic and experienced builders anxious to join our team. Mark has had to redesign our wall panels so that they can now be built on site (rather than the factory), using updated modern framing methods. His new wall system is pretty exciting. One in which he might actually like even more than before! He will write a post about it, because it’s worth writing about. Something new that can open up the doors for blah blah blah… (I say blah, but it’s very fascinating. Blah is because I’m not sure how to explain it.)

Now the ball is back in our court. We’ve got structural engineer looking at the new wall system. He should be giving us his feedback and stamp this week so we can finally get the city all of the drawings it needs to issue our permit. Quelle relief that will be.

This is what comfort looks like

Mark has been doing ‘thermal bridge calculations’ on our house. With Passivhaus, the goal is to make the building as air-tight and insulated as possible. Weaknesses often lie in the details —where differing materials connect or gaps occur. Obviously we don’t want any weaknesses. We want a fortress of thermal resistance, which is exactly what Mark’s models are showing.

The image above is a thermal bridge calculation on where our walls meet the slab. By all accounts, it looks excellent. Uniform heat distribution throughout. The inside sits at a comfortable 20•C and the outside at 0•C. If we had any gaps or weaknesses you’d see the warmer colours leaching their way out to the exterior. Instead, we have magical, rainbow coloured walls :)

3 tools to help us stay organized

Binder (above) and OmniPlan timeline (below)

Binder (above) and OmniPlan timeline (below)

In order for us to successfully GC our house build we’ve got to be mega organized. We’re getting there. We have assembled three key tools:

  1. The binder — our physical catch-all for anything and everything house related. Quotes, invoices, business cards, drawings — you name it.
  2. The project plan — we’re using OmniPlan for the project scheduling — to help us visualize tasks and timelines with its fancy dance Gantt charts
  3. The master budget spreadsheet — we’re not just using any old spreadsheet here — our spreadsheet is on steroids. Mark has created a user-friendly and powerful Filemaker database. It keeps track of all quotes and costs, compares numbers against our budgeted numbers and will act as our main digital repository.

There may not be a hole in the ground yet, but we’re getting the ducks lined up so that we can *hopefully* hit the ground running once we get a green light.

GC’ing our own home

It's not a Meghan and Mark blog unless awkward photos are involved

It's not a Meghan and Mark blog unless awkward photos are involved

You may have noticed that our site has been rather silent over the past month. That’s because we have been contemplating and figuring out how exactly we are going to build it, and equally importantly, how we are going to pay for it. After much deliberation, we have decided that we are going to take on the general contractor (GC) role of our build. It’s not something we were that keen to take on, seeing how are lives are more than busy as-is, but we see it as our only choice. It is the one thing that will dramatically cut costs for us (by at least 25%—if we don't screw it up). While we appreciate the service and value that a real General Contractors can bring to a job, it’s just not in the cards for us. Besides, we like to get our hands dirty.

It will be an invaluable learning experience for Mark, as the architect. Speaking of acquiring new skills as an architect, he has also taken it upon himself to draw up the structural panels that determine how our house will come together using a panelized pre-fabricated system. This is the step that has been stalling us and is what the city has been waiting for. Our house is deceivingly complicated and was causing some trouble for our builder. Rather than wait, Mark ploughed ahead. It was a worthy exercise to undertake by the sounds of things. Understanding the structure and where each and every truss is, he can see that moving a window half an inch to the left means that the house becomes significantly easier to build. He can then adjust the design accordingly. Neat stuff. Hopefully he’ll write about this.

So there you have it. We are the builders. Our blog will become ever the more fascinating. Now that the structural is near-complete, we should have everything the city requires for permit by the end of the week. We’re starting to get excited again.

April turns to May

The warm weather has arrived. Our lot is ready and waiting for our house. We’re hoping for a start date soon. While there may be no signs of progress from the lot, much has been going on in the background. Here’s a little update on what we’ve been working on since the snow has melted.

As I mentioned earlier, our drawings are in for permit. Our permit is being help up at the moment as the city is waiting for us to provide them with some technical details. We are waiting for our pre-fab builder to provide us with these missing details. We’ve been bugging him and he keeps saying ‘they’re coming’. We’ll see. Hopefully we can connect and sort this out ASAP. You reading this Adam?

We met with our Kitchissippi ward Councillor Jeff Leiper, thanks to a suggestion from one of our followers. We introduced him to the project, to the Passivhaus standard, and got him interested in what will potentially be one of the first homes certified under Passivhaus, and certainly one of the first infill projects to pursue the standard. (I say potentially, because there may be a couple others going for certification this year). We also brought up the issue of waiving or lowering development fees for projects like ours that will put significantly less stress on the city’s infrastructure. He agrees it’s a good idea, but we will likely never realize the benefits of lobbying this issue with our build. Perhaps we will be paving the way for future builds. Urban infill development is a contentious issue. Done poorly, it has the potential to really alter the fabric of a community, in a negative way. Clearly, this is not our intent, which is probably why Jeff was interested in hearing about our project. People in our corner of Hintonburg are passionate about where they live. And so are we. 

On the subject of HIntonburg-ers, A couple weeks back, we invited our immediate neighbours over to walk them through our designs. We want to ensure relations are kept neighbourly. Unfortunately, they’ll have to put up with some construction mess this summer. The orange house was built only a couple summers ago, so they’re definitely sympathetic to the cause. And hopefully our yellow house neighbours will be too. I think they can appreciate that we considered all three houses — how they work together and react to one another — in the design. We couldn’t have asked for better neighbours.

And finally, we’re still negotiating scope and prices with a GC to help us get started on phase 1 — site prep through to interior framing. The build is getting real. We’re looking at costs in earnest and at ways to bring them down. 

Start date? It’s still TBD. We’re anxious to get this ball rolling rolling rolling. Stay tuned.